M.D. OF BONNYVILLE – More than .4 million remains listed as unspent capital project funding in the M.D. of Bonnyville’s latest financial report, prompting questions from councillors about where the money is being held and how the municipality manages its reserves.
During the November 10 regular council meeting, Councillor Josh Crick questioned the remaining capital project budget, while Councillor Caroline Palmer asked about historical reserve accounts and the municipality’s investment practices.
The discussion came as council reviewed its unaudited financial statements for the third quarter ending September 30, 2026.
The M.D.’s capital project work-in-progress report lists an approved budget of approximately $24.44 million, with $7.28 million recorded in project expenditures and approximately $17.42 million reported as remaining variance.
However, the totals in the report do not fully reconcile, leaving a difference of approximately $264,000 between the reported variance and the amount calculated by subtracting expenditures from the approved budget.
Where is the $17.4 million?
Crick wanted to know where the money allocated to unfinished capital projects was being held.
“That’s still in the variance category, meaning that we’re still waiting to spend that?” he asked.
Administration confirmed that was correct.
Crick followed up by asking whether the funds were sitting in reserves or another account.
“And is that money sitting, like, in various reserves, or is it in the cash reserve, or where would that be?”
Administration explained that the municipality reviews its cash flow at least monthly, keeping available money in savings or investments until payments are required.
Funds are transferred into operating accounts as invoices arrive.

Crick continued pressing for clarification.
“Like, it’s got to be sitting somewhere because it’s not spent yet. I just wonder where it’s actually sitting,” he said.
Administration indicated the funding would likely be reflected in the municipality’s high-interest savings account.
The financial statements provide a broader picture of the M.D.’s holdings.
As of September 30, the municipality reported approximately $12.58 million in cash and temporary investments, along with $222.57 million in investments.
Those balances represent the municipality’s overall financial position, not a separate account containing the $17.4 million in remaining capital project budgets.
Major road and bridge projects account for millions
The work-in-progress report shows that a substantial portion of the remaining capital budget is associated with transportation infrastructure.
Among the largest outstanding project balances are:
- Township Road 610, Range Road 460 to Range Road 453: $6.08 million remaining from an $8.08 million budget, with 25 percent reported complete.
- Bridge BF-76626, Range Road 490 south of Township Road 643A: $1.89 million remaining, with four percent reported complete.
- Bridge BF-72752, Township Road 593A west of Highway 657: $1.60 million remaining, with five percent reported complete.
- Bridge BF-72115, Township Road 640 east of Range Road 472: $1.17 million remaining, with five percent reported complete.
- Bonnyville Regional Airport upgrades: $1.13 million remaining, with approximately six percent reported complete.
- Bridge BF-73061, Range Road 450A north of Township Road 641: $1.02 million remaining, with seven percent reported complete.
The airport upgrades include planned security fencing and gates, taxiway improvements and engineering work associated with a proposed runway extension.
Several projects listed in the report have completion dates approaching at the end of 2026, while others extend into 2027 or beyond.
The report also identifies some projects with little or no recorded spending.
These figures reflect expenditures recorded as of September 30. They do not necessarily indicate that construction has stopped or that projects are behind schedule, as work may be underway before invoices are processed.
More than $116 million in municipal reserves
The M.D.’s financial statements also show $116.65 million in reserve assets as of September 30, up from approximately $100.55 million at the beginning of the year.
Some of the larger reserve balances include $41.74 million in the cash flow reserve, $37.89 million in the equipment replacement program, $15.61 million in the bridge reserve and $5 million in the road infrastructure reserve.
These funds are designated for different municipal purposes and are not all available for general spending.
During the meeting, Palmer questioned two smaller reserves that have remained on the municipality’s books for years.
The first was the M.D. school reserve, which had a balance of $138,114.
Palmer asked whether the account originated from an old arrangement involving school boards.
“Do you know where that money came from?” she asked.
Administration acknowledged that the reserve was historical and agreed to investigate its origins and report back to council.
Is an old grant reserve still needed?
Palmer also questioned the community action grant reserve, which held $126,880 as of September 30.
“Why do we have a community action grant reserve?” she asked.
Administration explained that the reserve had been established years earlier, with the intention of eventually reducing its balance to zero.
Staff indicated they did not believe the municipality was continuing to contribute to the reserve.
Palmer asked whether the money could be transferred out of the account.
Administration explained that council could authorize a transfer through a motion.
The discussion concluded with agreement that the matter could be revisited during budget deliberations.
No transfer was approved at the meeting.
Investment income exceeds budget
Palmer also asked whether provincial legislation restricts where municipalities can invest public money.
Administration explained that Alberta’s Municipal Government Act places restrictions on certain types of investments, including stocks and bonds.
The financial statements show the M.D. earned approximately $5.30 million in investment income during the first nine months of 2026.
That is approximately $2.05 million above the municipality’s full-year investment income budget of $3.25 million.
Overall, the M.D. reported $135.83 million in revenue through September 30, slightly exceeding its full-year budgeted revenue of $135.73 million.
Recorded expenses totalled $88.42 million, or 65 percent of the annual expense budget, according to the statement of operations.
The municipality also reported net financial assets of $223.39 million as of September 30.
Council accepts financial report
Following the discussion, Councillor Ed Duchesne moved to accept the third-quarter unaudited financial statements as information.
The motion carried.
While no changes to reserve allocations or investment practices were approved, the discussion raised questions that could return as council reviews future spending priorities.
For now, the financial statements show significant capital work still budgeted, substantial municipal investments and several historical reserves that councillors want to better understand.
Help us stay Connected! If you enjoy our content, consider giving us a small tip. Your $2 tip helps us get out in the community, attend the events that matter most to you and keep the Lakeland Connected! Use our secure online portal (no account needed) to show your appreciation today!
Share This Story, Choose Your Platform!
M.D. councillors question $17.4 million in remaining capital project budgets
M.D. OF BONNYVILLE – More than .4 million remains listed as unspent capital project funding in the M.D. of Bonnyville’s latest financial report, prompting questions from councillors about where the money is being held and how the municipality manages its reserves.
During the November 10 regular council meeting, Councillor Josh Crick questioned the remaining capital project budget, while Councillor Caroline Palmer asked about historical reserve accounts and the municipality’s investment practices.
The discussion came as council reviewed its unaudited financial statements for the third quarter ending September 30, 2026.
The M.D.’s capital project work-in-progress report lists an approved budget of approximately $24.44 million, with $7.28 million recorded in project expenditures and approximately $17.42 million reported as remaining variance.
However, the totals in the report do not fully reconcile, leaving a difference of approximately $264,000 between the reported variance and the amount calculated by subtracting expenditures from the approved budget.
Where is the $17.4 million?
Crick wanted to know where the money allocated to unfinished capital projects was being held.
“That’s still in the variance category, meaning that we’re still waiting to spend that?” he asked.
Administration confirmed that was correct.
Crick followed up by asking whether the funds were sitting in reserves or another account.
“And is that money sitting, like, in various reserves, or is it in the cash reserve, or where would that be?”
Administration explained that the municipality reviews its cash flow at least monthly, keeping available money in savings or investments until payments are required.
Funds are transferred into operating accounts as invoices arrive.
Crick continued pressing for clarification.
“Like, it’s got to be sitting somewhere because it’s not spent yet. I just wonder where it’s actually sitting,” he said.
Administration indicated the funding would likely be reflected in the municipality’s high-interest savings account.
The financial statements provide a broader picture of the M.D.’s holdings.
As of September 30, the municipality reported approximately $12.58 million in cash and temporary investments, along with $222.57 million in investments.
Those balances represent the municipality’s overall financial position, not a separate account containing the $17.4 million in remaining capital project budgets.
Major road and bridge projects account for millions
The work-in-progress report shows that a substantial portion of the remaining capital budget is associated with transportation infrastructure.
Among the largest outstanding project balances are:
- Township Road 610, Range Road 460 to Range Road 453: $6.08 million remaining from an $8.08 million budget, with 25 percent reported complete.
- Bridge BF-76626, Range Road 490 south of Township Road 643A: $1.89 million remaining, with four percent reported complete.
- Bridge BF-72752, Township Road 593A west of Highway 657: $1.60 million remaining, with five percent reported complete.
- Bridge BF-72115, Township Road 640 east of Range Road 472: $1.17 million remaining, with five percent reported complete.
- Bonnyville Regional Airport upgrades: $1.13 million remaining, with approximately six percent reported complete.
- Bridge BF-73061, Range Road 450A north of Township Road 641: $1.02 million remaining, with seven percent reported complete.
The airport upgrades include planned security fencing and gates, taxiway improvements and engineering work associated with a proposed runway extension.
Several projects listed in the report have completion dates approaching at the end of 2026, while others extend into 2027 or beyond.
The report also identifies some projects with little or no recorded spending.
These figures reflect expenditures recorded as of September 30. They do not necessarily indicate that construction has stopped or that projects are behind schedule, as work may be underway before invoices are processed.
More than $116 million in municipal reserves
The M.D.’s financial statements also show $116.65 million in reserve assets as of September 30, up from approximately $100.55 million at the beginning of the year.
Some of the larger reserve balances include $41.74 million in the cash flow reserve, $37.89 million in the equipment replacement program, $15.61 million in the bridge reserve and $5 million in the road infrastructure reserve.
These funds are designated for different municipal purposes and are not all available for general spending.
During the meeting, Palmer questioned two smaller reserves that have remained on the municipality’s books for years.
The first was the M.D. school reserve, which had a balance of $138,114.
Palmer asked whether the account originated from an old arrangement involving school boards.
“Do you know where that money came from?” she asked.
Administration acknowledged that the reserve was historical and agreed to investigate its origins and report back to council.
Is an old grant reserve still needed?
Palmer also questioned the community action grant reserve, which held $126,880 as of September 30.
“Why do we have a community action grant reserve?” she asked.
Administration explained that the reserve had been established years earlier, with the intention of eventually reducing its balance to zero.
Staff indicated they did not believe the municipality was continuing to contribute to the reserve.
Palmer asked whether the money could be transferred out of the account.
Administration explained that council could authorize a transfer through a motion.
The discussion concluded with agreement that the matter could be revisited during budget deliberations.
No transfer was approved at the meeting.
Investment income exceeds budget
Palmer also asked whether provincial legislation restricts where municipalities can invest public money.
Administration explained that Alberta’s Municipal Government Act places restrictions on certain types of investments, including stocks and bonds.
The financial statements show the M.D. earned approximately $5.30 million in investment income during the first nine months of 2026.
That is approximately $2.05 million above the municipality’s full-year investment income budget of $3.25 million.
Overall, the M.D. reported $135.83 million in revenue through September 30, slightly exceeding its full-year budgeted revenue of $135.73 million.
Recorded expenses totalled $88.42 million, or 65 percent of the annual expense budget, according to the statement of operations.
The municipality also reported net financial assets of $223.39 million as of September 30.
Council accepts financial report
Following the discussion, Councillor Ed Duchesne moved to accept the third-quarter unaudited financial statements as information.
The motion carried.
While no changes to reserve allocations or investment practices were approved, the discussion raised questions that could return as council reviews future spending priorities.
For now, the financial statements show significant capital work still budgeted, substantial municipal investments and several historical reserves that councillors want to better understand.
Help us stay Connected! If you enjoy our content, consider giving us a small tip. Your $2 tip helps us get out in the community, attend the events that matter most to you and keep the Lakeland Connected! Use our secure online portal (no account needed) to show your appreciation today!
Share This Story, Choose Your Platform!
you might also like
news via inbox
Get Connected! Sign up for daily news updates.